Example of construction work quote

This insurance is of importance for students or professionals in construction, architecture, civil engineering or people related to construction sites (houses, buildings, etc.) who want to have a format or basis to make their respective quotes , so here we go.


Ejemplo de cotización obra de construcción

It should be noted that for the tables (where we will develop the items to quote) you can work in Excel, and then yes paste them in Word or in our text editor. This for ease, and so that we have more formatting options. The rest is by way of letter, where it will go city, date, recipient, subject, brief introduction, quote as such, notes, farewell, signature and annexes.

Bogota, 22 January 2014

Gentlemen: Dr. [TO THE PERSON TO WHOM IT IS PRESENT]

Address: Calle 1 No. 1 – 01 Victoria Park [example]

REF: COTIZATION

Present it in order to submit the quote for your project BUILDING PEPE SIERRA, in accordance with the contractual obligations proposed by you.

ITEM

DESCRIPCION

UND

CANT

 VR UNITARIO

VR TOTAL

4CIMENTACION 

4,1

Poor Concrete Cleaning Thickness e=5cm  f’c=2000 psi

M2

   1.082,07        4.000

$ 4.328.280

4,2

Thick subfloor plate e 10cm and concrete e= 10cm y concreto f’c=3000 psi

M2

       146,54     15.000

$ 2.198.100

4,3

Lightweight foundation plate h=1.00 m con torta superior de 6 cm

m2

       935,62     60.000

$ 56.137.200

4.4.

Cyclopean concrete

M3

         70,00     90.000

$ 6.300.000

4,6

Reinforced concrete containment walls f’c=3000 psi

M3

         64,75   260.000

$ 16.835.000

4,7

Dice in reinforced concrete f’c=3000 psi

M3

         31,47   150.000

$ 4.720.500

4.9

Reinforcement steel piles and sweeps in particular

Kg

 18.791,00           240

$ 4.509.840

4.10

Reinforcement steel foundation beams

Kg

 25.914,00           240

$ 6.219.360

4,11

Reinforcement steel retaining walls

Kg

   8.400,00           240

$ 2.016.000

4,13

Electrowelded mesh subfloor plate

Kg

   3.488,00           240

$ 837.120

4,14

Headways of Pilots

Ml

       210,00     35.000

$ 7.350.000

4,15

Geomembrane under foundation plate

M2

   1.082,16        1.500

$ 1.623.240

4,17

Guide beam sweeps

M3

           3,57   260.000

$ 928.200

4,18

Passes drainage cassettes to pit ejector Ø 3″

ML

       180,00        1.500

$ 270.000

$ 0

 

5ESTRUCTURA

5,1

Lightened mezzanine plate of h=50 cm without bottom cake

M2

   5.818,00     65.000

$ 378.170.000

5,2

Concrete columns of 5.000 psi

M3

         62,92   260.000

$ 16.359.200

5,3

Concrete screens of 5.000 psi e= 20 cm

M3

         46,00   260.000

$ 11.960.000

5,4

Concrete screens of 5.000 psi e= 15 cm

M2

         56,55   260.000

$ 14.703.000

5,5

Concrete ladder of de 3.000 psi

M3

         46,28   280.000

$ 12.958.400

5,6

Concrete tank of 3,000 psi Water Reserve, includes PVC tape, gaskets

M3

         14,54   260.000

$ 3.780.400

5,7

Concrete tank of 3,000 psi fire, includes PVC tape, gaskets

M3

         16,18   260.000

$ 4.206.800

5,8

Reinforcement steel columns and curtain walls

kg

 42.777,00           240

$ 10.266.480

5.9

Steel reinforcement plate lightened mezzanine

kg

 86.552,00           240

$ 20.772.480

5.10

Stair reinforcement steel in concrete

kg

   1.500,00           240

$ 360.000

5,11

Tank reinforcement steel in concrete

kg

   2.800,00           240

$ 672.000

5,12

Electrowelded mesh lightened mezzanine plate

kg

   2.000,00           240

$ 480.000

5,13

Solid plate of cover e=10 cm

M2

         76,00     58.000

$ 4.408.000

5,14

Concrete ramp e=10 cm

M2

         79,50     65.000

$ 5.167.500

$ 598.537.100

A 2%

$11.970.742

I 2%

$11.970.742

U 3%

$17.956.113

$ 640.434.697

 

Notes

  1. New stretcher is offered for the first floor plate, for the finish in sight, vocelalala all the beams (this for a good finish).
  2. For columns and basement walls we offer new wooden forlat in yellow (to guarantee concrete to the eye); or used metal forticon.
  3. The contractor shall supply the necessary equipment for the execution of the work, such as pens, polishing machines, drills, concrete mixer, compressor, motor pumps, hammers, demolisher, frog and other tools required.
  4. We request a 5% advance on the value of the contract.

We appreciate your attention and are looking forward to a prompt response.

Cordially

[NAME OF PERSON LISTING]
Id: [Number], [city]
Phone: [Contact Phone Number]

The A-I-U is an additional tax that in some cases must be included in the quote for concepts of A (administration), I (unforeseen), and U (utility).

Many times, the success of achieving a good contract, or several of them, is that relevant and very accurate quotes are made. None of these details presented should be ignored, as there would be a greater likelihood of not obtaining a tender or business. Accuracy of products and services, presented in a strategic manner, but without going outside the format of an economic proposal document.

According to the specialists, everything should be specified in the document, but in a way that the figures and complexity of the matter do not frighten the prospective client. It is best to first investigate how a quote is professionally written and be very aware of the prices that are handled in the market.

Example of construction work quote
Source: Education  